Wednesday, February 2, 2011

Day 154 - Chugging Along

The installation of all cabinetry throughout the house began on Monday. This includes the kitchen cabinets, bathroom vanities, laundry cupboards and a drawer unit in the media room. One slight issue, that unit is supposed to be in the master bedroom, NOT the media room! Need to make a note and speak to D...oops!

We were excited to the underfloor heating for both the main and ensuite bathrooms has also been laid. Couldn't think of anything more useless in this heat right now but I'm sure it will be lovely to have come winter :)

A drive by the house this morning and I spied more tradies YAY! The sparky was back and had erected the steel pole which will connect us up to the grid. Not a moment too soon for the tradies running off battery power this week.


View from across the street on day 154


Kitchen cabinets and soft closing drawers aahhh! All in white poly

View to kitchen from leisure room

The splashback will be 'white float II' (looks like a pale green) and ceaserstone benchtops in 'ice snow'

Pantry doors in white poly



The drawer unit installed in the media room that should be in the master bedroom!

The concerning gap in the media room

Laundry - view from outside

Laundry cabinets in Oyster Linea, there is a broom cupboard to the left too

Main bathroom with waterproofing and underfloor heating
 
Main bathroom vanity in 'Licorice Linea'

Ensuite shower


Ensuite vanity in 'Licorice Linea', waterproofing and underfloor heating

3 comments:

  1. Fantastic news Rachael, looks great! Has your SS given you an approx completion date?

    ReplyDelete
  2. Looking fabulous Rachael!

    We are having underfloor heating too, as you say, last thing you want right now but in Winter we will be happy and our toes will be toasty!

    ReplyDelete
  3. Our SS was a bit reluctant to give a date. He said 'roughly early April' but will give us a definite about a month out from completion.

    ReplyDelete